Traffic chaos on the N-332 bypass through Torrevieja is reaching critical levels, with an average of 55,000 vehicles using the road daily on peak summer days. The road’s long-overdue widening project remains stuck in bureaucratic limbo, despite being greenlit environmentally, while congestion spirals out of control.

According to data from Spain’s Ministry of Transport, this four-kilometre bottleneck, particularly between the CV-905 and CV-95 junctions near Torrevieja’s hospital, now sees nearly 43,000 vehicles a day on average annually. But during July and August, traffic routinely soars past 52,000 vehicles, hitting 55,000 on Thursdays and Fridays, setting a new record for volume and pushing the road system to the brink.

Chronic Congestion with No Relief in Sight

The N-332’s bypass near Torrevieja, designed decades ago for lighter traffic, is now wholly inadequate for current demand. The traffic monitoring point at kilometre 53 near ‘la altura de Ferrís’ shows the road carrying 97% light vehicles and just under 3% heavy vehicles. Foreign-registered vehicles make up less than 7%, a surprisingly low number considering the area’s popularity with international tourists and expats.

Congestion is worst during the summer, but even in the “off-season” months of December, January, and February, daily vehicle counts hover around 35,000.

While the bypass is dual carriageway at the point of measurement, the most problematic stretch still consists of a single lane in each direction. This discrepancy means real congestion levels are even higher than official figures suggest.

Ripple Effects Across Torrevieja and Orihuela Costa

The daily gridlock on the N-332 has a domino effect on surrounding roads. Long tailbacks are common on the CV-95 near the roundabout by Torrevieja University Hospital and on the CV-905, whose roundabouts regularly clog up with overflow traffic.

Other previously viable alternatives, like Urbano Arregui and Desiderio Rodríguez avenues, have become just as saturated, regularly choked with local and commuter traffic. Even trying to divert via Orihuela Costa now leads directly into fresh jams, including on Avenida de los Escorpiones and at the Avenida de las Olas junction in Rocío del Mar.

The only road access to neighbourhoods like Cala Dorada and Rocío del Mar is effectively paralysed during peak summer days.

The General Directorate of Traffic (DGT) has been issuing daily congestion warnings for the N-332 between kilometres 54 and 58, active from 8 a.m. and lasting well into the evening, an average of 12 hours a day, every day since the end of the pandemic.

Widening Project: Approved but Still Stalled

Despite the crisis, there’s still no confirmed timeline for fixing the problem. The Ministry of Transport received environmental approval for a project to widen the N-332 back in February 2024. The plan includes expanding 4.47 kilometres of the bypass between the CV-95 junction and the bridge on Avenida Rosa Mazón, adding an extra lane in each direction. The estimated cost is €55 million, VAT included.

However, the final project has yet to be released for public consultation, meaning the tender process and construction remain months, or even years, away. Notably, the widening excludes another key four-kilometre stretch between Avenida Rosa Mazón and Alto de la Casilla, leaving a major choke point unresolved.

Behind Closed Doors: Political Backstory of a Stalled Project

The project’s stagnation has also been marked by murky political dealings. In late 2019, just before the COVID-19 pandemic, Torrevieja’s Mayor Eduardo Dolón met with then-Minister of Transport José Luis Ábalos to push for progress. Also present was an advisor to Dolón and a prominent Vega Baja businessman who had helped set up the meeting after months of formal requests.

The meeting, held in Madrid, lasted less than 30 minutes and, according to those familiar with the encounter, focused solely on the road expansion. However, it later became controversial when Ábalos’ advisor at the time, Koldo García, was implicated in multiple corruption investigations involving kickbacks and bribery for public contracts. García was even accused by businessman Víctor de Aldama, in a TV interview, of threatening Mayor Dolón, an allegation the mayor firmly denies, stating he has never met García.

While the meeting did little to unblock the project at the time, the environmental approval in early 2024 finally moved the needle. Yet, with no tender issued and no construction start date in sight, Torrevieja’s residents and visitors regularly find themselves stuck, literally and figuratively, in a long, long queue of traffic.